Future site of Apple's Sapphire Glass Manufacturing Facility |
An additional 129-acre second-phase parcel was leased
from DMB with plans for a similar facility. In 2012 the subject building
was constructed- featuring 1,341,492 SF of improvements per assessor
calculation on an 83.17-acre site. First Solar had intended to use the facility to
manufacture cadmium telluride photo-voltaic modules, but the site was never commissioned for manufacture
and was instead used for operations, maintenance, & inventory. Financial
filings indicate First Solar realized an $56.6M asset impairment for the Mesa
facility in its third quarter filing with the SEC.
On October 3rd 2013, First Solar entered a
purchase agreement to sell its Mesa assets and later split the 133 acre first
phase parcel into a 50-acre land portion and 83 acre factory site. VIZZDA
reported on October 8th, 2013 that Coolidge, Arizona-based
Bright International acquired the 50 acre land parcel at $1.60 PSF. The buyer
for the 1.3m+ SF building is Platypus Development LLC- which although no direct
entity linkage is made to Apple Corporate—all correspondence relating to the
sale is in care of Phoenix, AZ-based law firm, Greenburg Traurig—an announcement
made by Arizona’s Governor confirms the purchase.
By:
Hadden Schifman
Managing Director
Vizzda.com