The acquiring entity secured $17.839m in new construction
financing with Alliance Bank of Arizona to begin construction on SkySong III—a
145,000 ft2 4-story research facility in the southwest quadrant of
the project. Plaza Cos., which is the master developer of SkySong I and II,
will continue in that capacity with assistance from Holualoa; the master
developers have enlisted DPR as the general contractor and Butler Design as the
architect. Groundbreaking is slated for Late September.
SkySong was developed under a Government Property Lease
Excise Tax arrangement with the City of Scottsdale, who is the master lessor of
the property. This arrangement calls for the City of Scottsdale to acquire the
property from the original developers and lease it back to them at a discount
to property tax payable in lieu of collecting said property tax for a period,
after which time the property tax liability and the ground lease rent are
roughly equivalent. This master ground lease was modified to reflect the new
leasehold ownership several days after the close of the sub-lease agreement.
By:
Paul Dionne
Director of Analytics
Vizzda.com